The basic cost approach estimates the improvements' cost new, subtracts their accrued depreciation, and adds the site's value. Keeping land separate avoids depreciating it as though it were the building. For a simplified example, $260,000 replacement cost less $40,000 depreciation plus $90,000 land value gives $310,000. Real appraisals require support for each figure.